STEP ONE: AREA OF THE TILE
INSTALLATION WILL BE COMPLETELY CLEANED AND FREE OF
DEBRIS AND POP
NAILS
STEP TWO: MIXTURE OF SYNTHETIC AND MORTER MIX WILL BE APPLIED
DIRECTLY ON THE SURFACE OF THE EXISTING PLYWOOD FLOOR FOR BETTER BONDAGE AND
SQUEAK FREE.
STEP THREE INSTALLATION OF THE SUB
FLOOR— CEMENT BOARD [DUROCK OR HARDYBACKER] INSTALLED DIRECTLY ON THE APPLIED
MORTER MIX AND FASTENED WITH 2INCH SCREWS FOR TILE DURATION AND LONGEVITY.
STEP FOUR THE TILE
INSTALLATION BASED ON YOUR CHOICE OF DESIGN AND STYLE FOLLOWED BY THE
APPLICATION OF THE GROUT COLOR OF YOUR CHOICE AND A SEALANT SOLUTION FOR